Featuring:
Cantarell Compression Platform Project INTEC Riser Engineering Group Note from the President Houston Ship Channel Tanker Terminal Expansion AM-6 Platform Project Construction Management Technology Conferences
Northstar Offshore Arctic Pipeline Project Update BP Amoco Contract Award Employee of the Quarter Horn Mountain Export Pipelines PSI (Private Sector Initiatives) Offshore Technology Conference 2000


Cantarell Compression Platform Project
Project Overview
Following completion of primary fabrication activities at CEC’s Tuxpan, Mexico yard and IH’s Tampico Yard, (see INTEC Summer 1999 Quarterly Journal), the AKAL GC Compression Platform Complex has been successfully installed offshore in the Bay of Campeche adjacent to PEMEX’s existing AKAL GR Production Complex. INTEC’s Facilities Business Unit was responsible for owner’s due diligence of structural engineering and marine installation aspects of this platform complex.

Platform jacket loadout and deck fabrication at the CEC Tuxpan, Mexico fabrication yard.The project commenced in September 1998, after award by PEMEX to Compania de Servicios de Compresion de Campeche, S. A. de C. V. (CSCC), a consortium consisting of Westcoast Energy, Marubeni and CFC/CCC. INTEC also provided due diligence services to CSCC to assess the design, fabrication and installation capabilities of the proposed EPCI contractor prior to the bid to PEMEX during April/May 1998.

Platform Complex
The compression platform consists of an 8-leg jacket in 140 ft water depth, supporting a 2-level process deck, compression modules containing Nuovo Pignone PGT25 turbine packages, Rolls Royce power generators and living quarters. The main compression platform is connected via a tripod-supported bridge to the existing AKAL GR Process Complex. It is also linked to a flare tripod via two bridges and an intermediate tripod. The lower deck weighed 1455 short tons, upper deck was 1630 short tons, and the compression modules were 920 short tons each.

Platform Installation
Compression platform and flare structures installed adjacent to existing process complex in the PEMEX Akal Field.During the installation phase, the INTEC team reviewed the installation engineering, witnessed loadouts and tie down of platform components, liaised with the marine warranty surveyors, and performed due diligence during offshore installation onboard the 2500-ton capacity derrick vessel STANISLAV YUDIN. We understand from Oscar Byington and John Burns, INTEC Senior Construction Supervisors, that the Sunday Barbecue Fiestas were the highlight of this phase!

INTEC Project Team
The INTEC team at the fabrication yard in Tuxpan (Charlie Corr, Paddy Devereux and Ken Christie) relocated offshore along with Alex Mayants and Jim Barnes for the hookup and commissioning phase. Felix Hammontree inspected the electrical buildings and living quarters fabrication in Houston, and witnessed acceptance tests at the TESLA facility. Stuart Smithson closely monitored welding/NDT and structural painting issues during fabrication in Tuxpan and Tampico.

CSCC and Westcoast Energy have expressed their appreciation of INTEC’s role throughout the project, and especially INTEC’s participation in the success of the important phases of the offshore installation, particularly during the deck and compression module lifts.

INTEC Riser
Engineering Group
INTEC Engineering has established an expanded Riser Engineering Group within the Marine Pipeline and Riser Business Unit. This group includes core capabilities for drilling, production and pipeline riser types and configurations. Extensive riser system design capabilities and experience include steel and flexible pipe risers, subsea and surface tree production risers and fixed and floating drilling and production risers for shallow, deep and ultra deep water field development options.

The INTEC Engineering Riser Group provides total project services for fixed, top tensioned, steel catenary, hybrid riser towers and various flexible pipe riser system configurations. The riser group offers all levels of engineering services for the full range of riser systems, including front end field development feasibility and cost studies, risk evaluations, conceptual, preliminary and detailed engineering design, procurement services including preparation and management of vendor work packages, preparation of invitation to bid (ITB) documents, construction management and inspection services, and overall project management.

Riser Group Team
INTEC has assembled a strong team of engineers with extensive in-depth riser system knowledge and experience. Analysis software available to the team includes the AQWA suite of programs for vessel motion analysis, MCS International FREECOM, MODES and FLEXCOM for frequency and time domain riser response, ORCAFLEX for general time domain response and installation studies, SHEAR7 for VIV fatigue assessments, and ANSYS for component local stress analysis and design. These computer programs operate on a network of high specification PC’s, and are supported by INTEC’s fully verified proprietary calculation and design procedures.

Dr. John Shanks has been appointed as Manager of the INTEC Riser Engineering Group. John has more than 25 years experience in riser systems engineering with operators, consultants and contractors. His project portfolio includes riser systems for Hutton, Snorre and Heidrun TLP’s, Teal Guillemot FPSO and Jotun FPSO. John has been leading the SCR engineering for the Texaco Agbami FPSO Project.

In addition to John, the group consists of 8 other riser system engineers with a wide range of engineering design, analyses and installation experience. With a combined Riser Group Photo Top left to right: Saadat Mirza, Antonio Critsinelis, John Shanks, Jonathan Jury and Jie Fang; Bottom left to right: Basim Mekha, Todd Riley, Andrew Trim and Slimane Bouabbane
experience of more than 120 years, and participation in numerous significant world class riser system projects, the team will provide best-in-class service to our Clients. This team will be supported by Dr. Andrew Palmer, INTEC’s newly appointed Corporate Technology Manager, particularly in the area of riser/soil interaction and technology development.

INTEC Riser Projects
Current INTEC projects having significant riser system content include the El Paso Prince Field Development. INTEC has been awarded the detailed design of the Export Steel Catenary Risers (SCRs) for the Prince Field. The 12 inch oil and 12 inch gas export SCRs will be connected to the Moses TLP in 1492 ft water depth in Ewing Bank 1003. This is the first time that INTEC will have complete responsibility for the detailed design of SCRs attached to a floating structure. The Prince SCRs will be designed for comparatively shallow water depth; the shallowest water depth to date for SCRs connected to a floating platform is1700 ft for the Morpeth TLP. For BP Amoco GOM deepwater field developments, INTEC has recently been awarded a contract by BP Amoco for the engineering of their deepwater pipeline systems in the GOM. One of the key technical areas associated with this work is the design of infrastructure in water depths in excess of 6,000 feet. Also, INTEC has recently completed a study for the BP Amoco Crazy Horse field based on new concepts and technology for deepwater exploration and production.

Houston Ship Channel Tanker Terminal Expansion

INTEC Engineering has provided engineering support to Oiltanking Houston, Inc. since June 1999, during the construction of a new dock. Oiltanking, an independent tank terminal operator, is a wholly owned subsidiary of a privately held German company, Marquard & Bahls, AG. Howard Jones, Senior Construction Engineering Specialist, was assigned to work at the Channelview, Texas (Houston Ship Channel) location and will remain on the project until commissioning which is scheduled for June 30, 2000.

INTEC Project Scope
Howard assisted Oiltanking engineers with various bid packages, review of bids, selection of contractors and daily coordination and monitoring of contractor activities. The work included land-based excavation, Completed dock structure with loading arms and fire monitor tower.hydraulic dredging, modification of existing pipe racks, installation of new pipe racks and pipe bridges, and installation of approximately six miles of piping for crude oil, condensate, bunker fuel, diesel oil, nitrogen, fire water and potable water.

Dock Expansion Excavation
Dock 8 was designed for 900 ft long tankers with a maximum draft of 40 ft. Docksite excavation was split into two phases. Articulated dump trucks moved approximately 550,000 cubic yards of soil to a nearby disposal area. Hydraulic dredges then pumped approximately 1,070,000 cubic yards of soil to a disposal site 2 miles away.

Breasting and Mooring Dolphins
Following excavation, four breasting dolphins and four mooring dolphins were installed on 54-inch to 84-inch diameter piles. Dock piling being installed with accessway structure in foregroundDolphin construction was followed by accessway and dock structures. Ancillary equipment was installed on the accessway and dock structure, including a gangway, hydraulic crane, fire monitor tower, operator room and two 16-inch diameter loading arms.

Pipe Rack and Utilities
Approximately one half mile of new pipe racks were installed to connect with existing pipe racks, and five new pipe bridges were installed over existing access roads. The product piping is connected to four separate manifolds within the existing terminal facilities, and new utility lines were connected to existing utility systems.

PSI (Private Sector Initiatives)

Volunteer Home Repair Program
Private Sector Initiatives (PSI), a nonprofit corporation, addresses community needs. Recognizing that many low-income, elderly or disabled homeowners are physically and financially unable to keep their houses in good repair, one of PSI's primary focuses is to restore home exteriors. Funded by donations, grants, public sector funds and the effort of volunteers working in home repair crews, all work is delivered at no cost to the homeowner. Through 1999, a total of 3,149 home exteriors have been restored by volunteer crews with the support of a coalition of contributors and crew sponsor organizations. This award-winning program has made a profound impact on Houston's inner-city neighborhoods.
PSI Project Under Way

INTEC Volunteer Team
On April 1 and April 8, an INTEC volunteer team under the supervision of Bill Philliber, INTEC Senior Project Manager, completed minor repairs and repainting of a house on the northeast side of Houston. INTEC team members included Bill Philliber, Bert and Karen Schultz, Dave McKeehan, Ron and Julie Ledbetter, Kim Clark, Steve and Amanda Huffer, Andrew Easton, Jason Falls, Ron Tucker, Ebere Chimezie, Dolly Ondrias, Mario Ruiz, and Michelle Lang. INTEC is pleased to be a volunteer work crew sponsor and sincerely appreciates the exemplary efforts of its volunteer team members. A well deserved thanks for a job well done.

BP Amoco Press Release

BP Amoco Awards Infrastructure Engineering Contract
HOUSTON, May 8/PRNewswire/ - BP Amoco (NYSE:BPA – news) today announced the award of contracts to Paragon Engineering Services Inc. and INTEC Engineering Inc., to do preliminary engineering work relating to new oil and gas transportation infrastructure to be developed in the Gulf of Mexico. This work follows on BP Amoco’s previously announced plan to build oil and gas transportation infrastructure to reach the deepwater Gulf of Mexico, where large discoveries have been made.

Paragon Engineering Services Inc. will focus on onshore and the continental shelf offshore pipelines and potential booster stations. INTEC Engineering Inc. will concentrate on deepwater infrastructure. Both companies will work closely with BP Amoco through the project review and appraisal process, and Paragon Engineering Services Inc. will additionally provide overall project administrative support to BP Amoco. Paragon Engineering Services Inc. and INTEC Engineering Inc. are both located in Houston.

"We are very anxious to get this work started,” said Jerry Wenzel, BP Amoco General Manager for this offshore transportation project, “as we prepare to build transportation systems to deliver this oil and gas to market.” The value of these contracts is approximately $8 million during the first year. The companies will help BP Amoco review and select routes, equipment, and transportation system components, leading to a system availability by the time the first of these fields is ready for production, as early as 2003.

Chief among the areas awaiting infrastructure development is the southern Mississippi Canyon, the southern Atwater Valley and the Green Canyon areas of the Gulf. BP Amoco is an international company involved in the exploration and production of crude oil and natural gas; refining, marketing, supply and transportation of hydrocarbons; and manufacturing. Source: BP Amoco Corporation

INTEC will have a direct role in realizing BP Amoco’s challenging ultra deepwater projects. The project team has just commenced initial planning for the various engineering activities. INTEC Project Team leaders include Alvin Alleyne (Project Manager), Bruce Chandler, Brian McShane, Gene Mullee and Jim Lentz.

AM-6 Platform Construction Management Project

Project Description
Sipetrol S.A. is installing its latest offshore platform, AM-6 at the entrance to the Straits of Magellan in Argentine waters. This is the largest platform development to date for Sipetrol. The AM-6 development consists of a drilling and production platform in 85 meter AM-6 Platform jacket arriving at the installation site.water depth with an 8-inch gas pipeline to the AM-5 Platform and a 6-inch oil pipeline to the AM-3 Platform.

Straits of Magellan
INTEC was selected by Sipetrol to manage the construction phase of the project as Sipetrol’s representative on board the contractor’s derrick/lay barge “Artefacto Naval (A/N) Yagana”. The contractor, ENAP Magallanes, was selected by Sipetrol to perform the work based on their past experience with similar projects in the area which is well known for severe weather conditions. Combination of strong winds, waves, currents and tides makes offshore tasks an everyday challenge.

Construction Program
INTEC’s scope of work includes on-site supervision and construction management of the jacket installation, cellar, production and drilling deck installation, Derrick Barge Yagana alongside the nearly completed AM-6 Platform.deck and modular
equipment interconnects, J-tube riser pull-ins, conventional pipeline riser installations and installation of 15 miles of offshore oil and gas pipelines. The project began in August 1999 and is scheduled for completion in August 2000.

INTEC Awarded Vastar Contract

Horn Mountain Export Pipelines
INTEC has been awarded a contract for preliminary engineering of the Horn Mountain Field export pipeline system. VASTAR and OXY plan to jointly develop the field, in Mississippi Canyon Block 127, which is located in 5,400 ft of water. Different development options are being considered, several of which include export SCRs and pipelines to shallow water platforms. The work includes design of deepwater risers and pipelines, cost estimates, preparation of marine survey and pipeline installation bid packages and subsequent bid evaluations. The INTEC Project Team includes Vural Dolen (Project Manager), Chris Tam, Antonio Critsinelis, Brad Meadows, Simon Bonnell, John Shanks, Jan Janardhanan, Diego Lamacchia, Todd Phillips and Dan Alcott.

Vastar Resources, Inc. Logo

Northstar Offshore Arctic Pipeline Project Update

Northstar Pipelines Installed
The world’s first subsea Arctic oil production pipeline installation was completed on April 15, 2000 with a dual pipeline bundle being lowered into a pre-excavated trench at Seal Island. BP Alaska’s artificial gravel island production facility is located 6 miles offshore in the Alaskan Beaufort Sea in 37 ft water depth. INTEC Engineers, Peter Bryce (left) and Glenn Lanan, next to the Northstar pipeline terminations on Seal Island, 6 miles offshore the Alaskan Beaufort Sea coastline.Pipeline trench excavation required approximately 5 weeks and pipeline bundle installation required an additional 3 weeks. Both pipelines were successfully hydrotested by the end of April, well before spring ice thaw and break-up. Natural gas is scheduled to start flowing to the production island through a 10-inch gas pipeline in September 2000, and oil is scheduled to start flowing from the production island to the TAPS onshore pipeline system through the second 10-inch pipeline in December 2001.

Lessons Learned
The oil and gas pipeline system final design required only minimal changes from the preliminary engineering design used to submit the 1996 State Right-of-Way permit application, through to the final as-built configuration. A limit state design approach for pipeline bending was used to address potential Arctic environmental loadings such as ice keel gouging of the seafloor and subsea permafrost thaw subsidence. A result of the very thorough Environmental Impact Statement and extensive pipeline regulatory review was the inclusion of a pipeline leak detection sensor strapped to the pipeline bundle. Extended reach backhoe excavates gravel island approach as sidebooms lower pipeline bundle 50 feet to seafloor trench through slot in the floating ice sheet.The subsea pipeline system integrity and leak detection capabilities are critical issues in an Arctic environment. Other lessons learned relate to: 1) welding and inspection procedures applicable for limit state pipeline design, 2) use of the stable landfast sea ice as a work surface during pipeline construction, 3) offshore trenching using extended reach backhoes, and 4) using conventional sidebooms to lower pipe 50 feet from the surface of the floating ice sheet to the bottom of the pipeline trench in water depths of 37 ft.

In addition to potential applications of Northstar Project experience for future subsea Arctic pipeline projects, limit state design for pipe bending is of particular interest. Pipelines exposed to potentially severe displacement-controlled bending loads can be designed to safely operate with strain levels many that far exceed conventional yield stress allowable levels.

A Note from the President
Or: Why did the slug cross the road?
On a recent long walk through a rainy countryside I had the opportunity to observe nature along my path, and reflect upon its many wondrous facets. Doing so I ran into a question I was not able to solve, and would like to put before you, the reader.

While walking along a narrow asphalted country road I noticed in the damp morning many a slug crossing the pavement. Although the traffic was very light, I observed that not all slugs managed to make it across, judging from their flattened remains. The question came up what chance a slug had to survive the crossing and whether the species even could be threatened by extinction. To help define the problem I took some measurements and made a number of assumptions that seemed reasonable based on my observations.

President Willem Timmermans

  • Slugs vary in length between 5 and 13 cm; it is reasonable to assume that the length of a slug (as for humans) follows a normal distribution.
  • A 10-cm slug was observed to move at 8 cm/min.; it appears that a slug moves at a speed that is directly proportional to its length.
  • Not all slugs move straight across; the angle seems to vary between +/- 45 degrees to a perpendicular to the road axis; no information was obtained regarding the probability distribution of this angle, but again, a normal distribution would seem reasonable.
  • The road is 4.5 m wide.
  • Cars drive normally in the middle, but move to the opposite side when passing a traveler on foot; all foot travelers are going in the same direction (west); only small cars were seen and an occasional farm tractor, passing on average every 9 minutes; in addition, about two horse or bullock drawn carts passed in an hour.
  • Foot travelers pass on average every 20 minutes.

The questions are: (1) what is the probability that a slug reaches the other side of the road; (2) how many slugs are gone before their time on an average spring day; and (3) are slugs threatened by extinction in that region?

I also noticed that worms crossed the road, and at much greater speed, but let’s leave this to another time.

Meanwhile there is nothing sluggish about business at INTEC. We are back in a steady growth mode and have been successful in capturing a number of major contracts that now amount to an order book of unprecedented size. This means a lot of hard work for all to keep up with the growth and project related movements. I want to particularly mention our support staff who have to arrange office space and computer facilities, introduce new staff, assure that the mail still gets delivered to the right place, and generally keep the wheels greased, often late at night or on weekends. Special thanks to you!

President Willem Timmermans

W. J. Timmermans
President

Technology Conferences

OTC 2000
Gene Mullee of INTEC Engineering corroborated with Alan Niedoroda, Chris Reed, Brian Parsons and Jim Breza of URS Greiner Woodward Clyde and George Forristal of Shell E & P Technology on a paper entitled “Developing Engineering Design Criteria for Mass Gravity Flows in Deepsea Slope Environments” which was presented at the OTC 2000 Offshore Technology Conference held May 1-4, 2000 in Houston, Texas. Also participating in the OTC were Glenn Lanan, Brian McShane and Andre Nogueira of INTEC and John Ennis of BP Amoco, with a paper entitled “Northstar Offshore Arctic Pipeline Limit State Design for Bending”. “Assessment and Evaluation of Deepwater, Continental Slope Geohazards” was also presented by Simon Bonnell and Gene Mullee of INTEC Engineering. These papers are available on the INTEC Engineering website at
www.intec-hou.com/news/technical/.

SSB Technology Bazaar
INTEC Engineering (SEA) Sdn. Bhd., participated in a Technology Bazaar held at Sarawak Shell Berhad (SSB) in Miri, Sarawak, Malaysia from May 22 to 24, 2000. Thirty-one companies including INTEC participated in the exhibition and technical presentations. Visitors to the exhibition and Basri Othman, INTEC (SEA) Marketing Coordinator, managed INTEC’s exhibit at the SSB Technology Bazaar.
participants in the presentations included engineers from SSB and Carigali Sarawak Operations, and representatives from Brunei Shell Production, Petronas Carigali (Kuala Lumpur) and Petronas Research. Exhibitors and speakers participating in the SSB Technology Bazaar focused on technologies for marginal field development, gas application equipment, subsea production and FPSO systems.

FPSO’s Present and Future
INTEC participated in a workshop conducted by the Offshore Technology Research Center featuring “FPSO’s Present and Future”, held in Houston, Texas on June 7-8, 2000. Ken MacKenzie, INTEC Floating Systems Business Unit Manager, was a panelist for the session entitled “Oil Storage and Offloading”. The workshop was sponsored by Minerals Management Service, the US Coast Guard and DeepStar.

Offshore Technology
Conference 2000

For the 3rd consecutive year, INTEC was an exhibitor at the OTC. INTEC’s exhibit featured deepwater field development projects with emphasis on deepwater riser systems. The exhibit included an interactive website and subsea project animations. Paul Kronfield and Danette Campbell (center) observing the action at OTC 2000.Eighty-six countries were represented at this year’s OTC, with more than 43,000 persons in attendance, many of whom visited the INTEC booth. There were 2,035 exhibiting companies from 30 countries. Paul Kronfield, Marketing Coordinator and Danette Campbell, Marketing Assistant, planned and managed INTEC’s exhibit.

Willem Timmermans, INTEC President, meeting with visitors at the INTEC exhibit.

Paul Chui - Employee of the Quarter

Paul Chui joined INTEC Engineering (SEA) Sdn. Bhd. in Kuala Lumpur in 1995 as Finance and Administration Manager, and has since successfully served three INTEC (SEA) general managers including Bert Schultz, Vural Dolen and currently, Indu Mahendran.

Paul completed his accountancy qualifications in 1981 and began his career by initially working as an internal auditor for a Public Listed Company in 1982. Paul and FamilyBefore joining INTEC, Paul held similar positions in a company distributing electrical appliances in East and West Malaysia, and a company who was an operator of a world trade convention and exhibition hall in the food and beverage industry.

Paul has more than 17 years experience in audit and accounting work. During his career, Paul has traveled to Los Angeles, California to oversee accounting functions for a hotel chain, and has traveled to the INTEC Houston office in 1996 and 1998 for familiarization and updating with INTEC corporate accounting software.

Paul and his wife Maria have two children. Mark, age 9, is attending Primary 3 this year, and Diane, age 6, will be in Primary 1 next year. Paul’s hobbies include listening to music, traveling and playing snooker. He and his family recently visited Penang Island off the northwest coast of Peninsular Malaysia for vacation, and to sample the world renowned Penang cuisine. Next planned destination is Langkawi Island during the December school holiday.


INTEC Engineering, Inc.
Intercontinental Building
15600 JFK Boulevard, 9th Floor
Houston, TX 77032, USA
tel: (281) 987-0800
Primary Fax: (281) 987-3838
Admin Fax: (281) 987-2002
e-mail: info@intec-hou.com
INTEC Engineering (SEA) SDN. BHD.
Suite 12.2, 12th Floor
Menara Aik Hua
Changkat Raja Chulan
50200 Kuala Lumpur, Malaysia
Tel: +60 (3) 202-2488
Fax: +60 (3) 202-3488
e-mail: info@intec-mal.com.my
INTEC Engineering B.V.
Poortweg 14
2612 PA Delft, The Netherlands
P.O. Box 3178
2601 DD Delft, The Netherlands
tel: +31 (15) 256-5675
FAX: +31 (015) 256-0194
email: info@intec-delft.com
INTEC Engineering S.R.L.
Lavalle #465
Planta Baja
1047, Buenos Aires
Argentina
tel: +54 (1) 14 327-4120
FAX: +54 (1) 14 327-4121
email: info@intec-hou.com
INTEC-egis
Adelaide House
200, Adelaide Terrace
Perth, Western Australia 6000
tel: + 61 (8) 9220 9374
FAX: + 61 (8) 9325 9897
email: info@intec-hou.com