![]() |
||
| |
||
| Spring 2003 | ||
| |
|
|
| |
||
| Pipeline Material Selection - 13 Chromium as an Alternative to Duplex |
|
High alloyed 13Cr Weldable Martensitic Stainless Steel (WMSS) has superior corrosion properties compared to the standard carbon steel, and is a viable option to the 22Cr Duplex Stainless Steels (DSS) provided the transported medium is not too corrosive. As a rule of thumb, the cost of 13Cr WMSS pipe material is half that of 22Cr DSS. 13Cr pipe has been utilized for a range of different projects worldwide during the last 6 to 7 years by Woodside, Statoil, Norsk Hydro, Esso, BP Amoco and Marathon.
During the last few years, the oil and gas industry has experienced several failures in 13Cr WMSS pipeline materials associated with either girth welds or anode pads. The main cause of failure has been attributed to the following three different mechanisms:
INTEC is currently evaluating the use of high alloyed 13Cr WMSS pipeline material for a project in Australia (temperature - 110 ¡C, H2S - 6 mbar, CO2 - 1.8 mol%). As part of this evaluation process, several of the current failure cases have been studied, in addition to having had discussions with some of the key personnel from the various research groups that are investigating these failure mechanisms. The key driving forces for the three above mentioned failure mechanisms are:
HISC:
SSCC:
Sensitization: Both of the internal failure mechanisms have only been observed in the "lean" 13Cr WMSS grades (low Ni and Mo). Laboratory testing has clearly demonstrated that a remedial action to reduce the probability of failure occurrence is to post weld heat treat (PWHT) the welds at 620 to 650¡C for 3 minutes. This testing shows an apparent reduction in the material's propensity to fail due to any of the above failure mechanisms when PWHT is applied. There is still some research required to fully explain the restitution mechanisms taking place during the heat treatment process.
To mitigate the risk for any of these failure mechanisms to occur, the following recommendations should be considered:
|
| |
||
|
Block 12 Shallow Oil Development and CHPS Pipeline Replacement Project
The Block 12 project consists of two new 16-inch multiphase and 20-inch gas interfield pipelines. The Casing Head Petroleum Spirit (CHPS) project comprises one new 10-inch condensate trunkline to the Seria shore including the onshore pipeline.
PID 029 is a DN250 CHPS condensate trunkline from AMRJ-02 platform to Seria Area Intake Station (SAINTS) Terminal installed in 1978 with a distance of about 22km. It is the most critical CHPS line in the offshore west Brunei water as it evacuates CHPS from Area 1 (AMPA-09) and Area 2 (AMPA-06) to SAINTS Terminal. The intelligent pigging results indicate that the pipeline has a wide range of metal loss features (minor to severe) with a deepest detected internal wall loss of 71%. It has been concluded that the pipeline will have a remaining life of 3 years and therefore its life span ends in Year 2003. As a result it has been determined a replacement will be required.
INTEC mobilized an engineering team to Brunei. The detailed engineering design was completed in March 2003 with the pipeline installation to take place in June 2003. T. Mohanadasan was managing the project from KL office, while Alipudin Majid led the project team towards the completion of the design work in Brunei. Kamarul Hisyam, Omar Mamat, K. Thavamoney, Othman Yusof, Sadiah Omar and Rozlinda Aziz have made significant contributions toward the success of this project. |
Cerro Dragon Crude Oil Treatment Plant
In October 2002, PanAmerican Energy (PAE) awarded INTEC-ARCAN a contract for the construction and installation of a crude oil treatment plant in the Cerro Drag—n Field, an area of San Jorge Bay in the southern Argentine province of Chubut.
The project comprises the enlargement and refurbishment of the existing plant, with all the associated operational and security restrictions. The plant collects crude oil from different wells for a first separation stage (water and sludge) prior to pumping the crude to either a pipeline or to storage tanks. The INTEC-ARCAN scope of work includes supply of all materials and equipment, performance of detail engineering based on engineering supplied by PAE, and execution of civil, mechanical and electrical works, as well as instrumentation installation. The contract period is 195 days, with an extra 45 days for commissioning and start-up of the facilities. All work should be wrapped up by July 7th. The project is 70% complete as of the end of April.
The following equipment and devices, among other items, are to be installed as part of our job:
All tasks are being performed in full compliance of the quality, safety and environmental standards as defined by the Integrated Management System which is in place at INTEC-ARCAN. |
|||
| |
||
| AskINTEC - Answers Anytime, Anywhere |
|
How does an engineer working alone in China get answers to questions about pipeline codes in other countries that might apply to a current issue he's tackling? In most situations, you'd either be out of luck or have to wait days or weeks to locate experts and documentation.
For INTEC's Julio Daneri, help was a few keystrokes away with AskINTEC. Using just the internet and a web browser, Julio tapped into part of INTEC's "brains." AskINTEC provides references to documents in INTEC's extensive electronic technical resources (knowledge base), as well as to INTEC subject matter experts and previous AskINTEC Q&A's. While Julio slept in China, experts in INTEC's Buenos Aires and Houston offices provided just the information he needed.
A query from a Houston project engineer was referred to a relatively new INTEC employee in the UK with more than 20 years' industry experience who had been working on an almost identical problem for about six months. The answer, received overnight, "provided a major contribution to the project," potentially shaving several months and saving considerable cost, according to the project lead engineer. INTEC engineer Stephen Lyon has shared his expertise by answering several questions during downtime while on a lay barge in the Mediterranean. Lyon accesses the AskINTEC questions by logging into webmail on INTEC's intranet. Lyon adds that INTEC's intranet itself provides valuable knowledge to remote employees. Lyon also has used AskINTEC to get input from colleagues around the world. How does AskINTEC work? AskINTEC users enter questions or searches via the intranet from anywhere in the world via standard web browser. Instantly the user gets both a list of all INTEC electronic resources (technical library, archives, codes, standards, specifications, recent Q&A and FAQ's, etc.) on the subject and a list of related experts. (See Diagram) If the documentation does not answer the question, the user can ask one or more experts to review and answer questions regardless of their physical location. Q&A's are indexed and saved for future reference. Questioners can also post questions on topical bulletin boards and browse "home pages" for various engineering disciplines. Paul Laws, global leader of INTEC's materials technology group and one of INTEC's most popular and responsive subject matter experts, says he prefers whenever possible to answer questions in AskINTEC instead of by e-mail, telephone, or personal visit, because he knows his answer will be saved and available for use by future questioners. While the Q&A format between questioner and expert is valuable, most information in AskINTEC queries actually is found via a search of existing INTEC documentation such as the technical library, project archives, and previous AskINTEC dialogs. AskINTEC helps INTEC greatly improve its knowledge base by identifying which documents are most useful and highlighting where current documentation needs improvement. In addition, every time an employee answers a question or adds a FAQ, resource, or Best Practice, Ask INTEC is learning what they know and automatically updating their skill profile. This provides INTEC increased and updated knowledge about who knows what in the organization.
Recent AskINTEC search and Q&A topics include:
AskINTEC is a proprietary customization of AskMe knowledge management software. AskMe is being used by leading companies such as Ford, Honeywell, and Boeing. To our knowledge, INTEC is the only company in its market sector broadly employing this kind of technology to its clients' benefit. |
| |
||
| |
||
| A Note from the President | ||
At an airport I passed through recently I saw a poster with the word "Thalassotherapy", and thought: that's us! Old Xenophon described the trek of a Greek army returning from battle in Persia around 400 BC and recorded their daily travails with a repetitiveness guaranteed to put to sleep student readers 2400 years later. As one of these students, I did remember that when the Greeks finally reached the Black Sea which indicated they were getting close to home, they exclaimed "Thalassa". The other Greek word "therapy" is still in use, so I thought "eureka" and realized that a healing marine practice fits as a description of what we do.
We provide these healing marine services to Clients who we make feel better by creating healthy projects. If we were getting paid more, one could actually think of our engineering discipline as thalassotherapeutic medicine. I believe that actually was the meaning of the poster I saw, as it depicted some seaside spa and a woman whose looks had obviously benefited from saline treatment. Whether this was by ingesting it or bathing in it was not clear, but it demonstrated how the sea can make you look good, something we try to do every day. We also find it therapeutic to ourselves to be busy with things under water and on the bottom of oceans. We have become familiar with that wet world as we design things that have to be installed there and operate for a long time. We study the behavior of the ocean currents and waves, and of the seabed so that what we design can withstand this environment. One of the more extreme hazards we sometimes need to take into account is the tsunami, enormous waves caused by submarine earthquakes. A recently published book about the 1883 eruption of the Krakatau volcano in Strait Sunda, between Java and Sumatra, describes how this cataclysmic event generated a wave of as much as 40 m high that slammed ashore on the nearby coasts of above mentioned islands and wiped out many towns |
and villages causing the drowning death of over 35,000 people. This wave sped around the world and was registered as far away as the Bay of Biscay, having traveled more than half the earth's circumference. The rest of the damage was done by the 11 million cubic km of pumice, rock and ash that was hurled 50 km high into the stratosphere, resulting in a change of the planet's weather for several years. Artists of the time like Frederick Edwin Church in the US and William Ashcroft in England painted the very vividly colored skies caused by all the volcanic dust.
Fortunately there is little oil or gas to be found in basalt as it comes up from deep in the earth at the place where the north-moving Australia plate dips under the Asia plate, but the effects of resulting earthquakes and volcanic eruptions can be felt at distant project locations. Such an event could cause severe "thalassotrauma" to our oil and gas facilities, but fortunately continental drift and plate tectonics are very slow processes, so that only one in many generations of thalassotherapists needs to worry about it. In the meantime let's keep looking good under water.
W. J. Timmermans |
|
| |
||
| Survey Group Helps INTEC Find Its Way |
|
INTEC's survey group, enjoying a steady workload, has always been very active. Over the past three years, however, the workload has grown dramatically. To accommodate this increase the group has increased in size from Simon Bonnell initially to our present 10 engineers. This increase in staffing in this important area has significantly extended the depth of experience, technical knowledge and range of skills we provide our clients.
The group is working on a wide variety of projects, ranging from Chevron Angola Project overall field layout to detailed route selection pipeline soil interaction studies for the BP Mardi Gras, Shell Bonga and Pioneer Harrier projects, and the Chevron Congo River crossing high-level concept studies. These projects integrate results from a wide range of data acquisition systems including ultra-high resolution bathymetry, sidescan sonar and state of the art CHIRP subbottom profiler data in water depths up to 7,500 feet. We are providing positioning oversight on pipeline installation, LBL array design, deployment and calibration, and ROV clearance and verification surveys. The expertise in the survey group is not limited to surveying in the classical sense. Being able to help someone decipher the more unusual mapping datums such as "Old Egyptian 1907 MRE" or even "Louisiana State Plane" is still gratifying. INTEC's Simon Bonnell is one of the most experienced all-round surveyors in the offshore industry. Marc Bik and Andrew Grubb bring their strong backgrounds in geotechnical field and theoretical work. Nigel Tootill is an expert in geophysical surveying and positioning, while Angus Reid is a geotechnical engineer who is well versed in pipeline design with a flair for software and rugby. James Nicholls has worked with just about every type of survey system and knows what to focus on, and Justin Brown is indispensable for his TerraModel andANSYS bottom roughness skills. Todd Phillips brings his experience in ocean engineering and pipeline design to the group, and Raymond Rojas, the most recent addition to the team, brings experience in civil engineering construction and oceanography. Martin Morrison has been kicking around the onshore/offshore investigation and construction survey world for nearly 20 years. While our team resides under the Pipeline Group umbrella, the other INTEC groups frequently turn to us for technical assistance in servicing their clients. Our experience in geotechnical data collection and design calculations has proven invaluable for a variety of fixed seabed structures, design and execution of ultra-high 3D seismic surveys for seabed installations and conductors. We have planned and completed bathymetry studies in water depths from 0 to 10,000 ft with resolution and accuracy in the subdecimetric range. Our expertise in this surface and subsurface positioning extends from preliminary field layout studies to installation and construction activities. We make maps that you can read and understand! We are working to expand in areas beyond INTEC's traditional oil and gas capabilities. We are in the process of consolidating our individual stand-alone expertise in nearshore skills in harbor, breakwater, shore protection and coastal development into a unified approach. The nearshore and coastal market is one of the most rapidly growing fields in development engineering as urban and environmental pressure on this narrow strip of land continues to grow. Expansion into these areas will make good alternative use of the high level of engineering expertise within INTEC. |
| |
||
Barbara Castellese - Employee of the Quarter
Barbara Castellese has been with INTEC since 1989 and since that time she has been responsible for a variety of duties. Her current position in the Human Resources department focuses on obtaining work visas and immigration visas ("green card") for the international personnel working in the Houston office. The green card program was initiated last year and Barbara did the initial research and document preparation, resulting in the submitting of over 30 Green Card applications for INTEC employees.
With her various duties over the years, Barbara has been on assignments to almost all of the INTEC operating offices. She keeps her passport current so she can complete the INTEC office circuit at the Perth office. Barbara was born in Washington, D.C. and her family still lives in Southern Maryland. One of her hobbies is traveling to escape cold snowflakes in the D.C. area to the warm and soothing areas of the Caribbean. She's a recent convert to the Winston Cup NASCAR racing circuit and has twice visited the Texas Motor Speedway for the races. Air Jamaica and NASCAR have teamed for several years to have an end of race year "Beach Bash" and Barbara, along with her posse (Connie Reeder, Kim and Michael Clarke) participated, mingling with the race car drivers, crew chiefs, pit crew members and garage staff while they relax before the start of the next season. Bowling and fitness are additional hobbies in Barbara's schedule. She participates in women's bowling tournaments at the city, state and national levels. The national tournaments are held all over the U.S. and a few of the diverse cities include Indianapolis, Indiana, Fort Lauderdale, Florida, Tampa, Florida, and this past March, Reno, Nevada. The prime location for Barbara's new fitness trend of weight training with free weights and machines is now 24 Hour Fitness. She's graduated from very low weights to leg presses of over 200 pounds. |
OFFSHORE: The Place To Be...
Whether working on a drilling rig, construction vessel, lay barge, or dive support vessel in the Gulf of Mexico, one thing that everyone experiences are the long, grueling and sometimes frustrating hours attempting to do one simple solitary task. There are usually at least 5-10 simultaneous operations happening at any one time on any offshore facility and a lot of noise to go along with these activities.
The working hours in the oilfield are usually described as tours (pronounced "towers") and start and end at noon or midnight. The logic is fairly simple, work 12 hours and sleep 12 hours because then you are only awake for half the time you are onboard, thereby reducing the number of days you are gone. This mental trickery works for some but not others. Being in a relatively isolated environment can be a positive or detrimental situation. It is usually positive because it allows everyone to focus on the job at hand and not have to worry about who is picking up the dry-cleaning or cooking dinner that night because those things are all done by others onboard. However, when your 12 hours of time off have expired, there is no doubt in these people's mind of what is expected of them. The work is extremely physical and demanding. Even though the majority of vessels used have some form of automation involved in the process, mechanical and human failures often lead to major ordeals and repairs. Everyone works for a common goal at the end of the day, accomplish the job, be safe, protect your work colleagues from unseen hazards, and be ready to get on the helicopter when your time is up. |
|||
| |
||
| INTEC Engineering, Inc. Intercontinental Building 15600 JFK Boulevard, 9th Floor Houston, TX 77032, USA tel: (281) 987-0800 Primary Fax: (281) 987-3838 Admin Fax: (281) 987-2002 e-mail: info@intec-hou.com |
![]() |
INTEC Engineering (SEA) SDN. BHD. Suite 12.2, 12th Floor Menara Aik Hua Changkat Raja Chulan 50200 Kuala Lumpur, Malaysia Tel: +60 (3) 202-2488 Fax: +60 (3) 202-3488 e-mail: info@intec-mal.com.my |
![]() |
INTEC Engineering B.V. Poortweg 14 2612 PA Delft, The Netherlands P.O. Box 3178 2601 DD Delft, The Netherlands tel: +31 (15) 256-5675 FAX: +31 (015) 256-0194 email: info@intec-delft.com |
![]() | INTEC Engineering S.R.L. Lavalle #465 Planta Baja 1047, Buenos Aires Argentina tel: +54 (1) 14 327-4120 FAX: +54 (1) 14 327-4121 email: info@intec-hou.com |
![]() |
INTEC-egis Adelaide House 200, Adelaide Terrace Perth, Western Australia 6000 tel: + 61 (8) 9220 9374 FAX: + 61 (8) 9325 9897 email: info@intec-hou.com |