![]() |
||
| |
||
| Q3 2004 | ||
| |
|
|
| |
||
| Anadarko Green Canyon 518 on the Fast Track to First Oil |
INTEC Engineering was awarded preliminary design of Anadarko's GC 518 subsea tieback to the Marco Polo platform on 31 December 2003, with an initial first-oil date of January, 2005. The initial scope of work included preliminary design work on pipe-in-pipe flowlines, insulated SCRs, flow assurance, subsea production and controls equipment, survey, permitting and project scheduling. Due to the fast-track nature of the project, our scope was expanded in April to include detailed engineering, procurement and execution support concurrent with the ongoing preliminary design. INTEC Engineering will continue to work with Anadarko on this project through to the Construction Management phase in November.
Location and Field Architecture
Three existing wells will be connected to a single production manifold; two through insulated jumpers and one through a pipe-in-pipe in-field flowline. See Figure 2 - System Isometric Overview (pg. 3). Initially a single well will be completed and tied directly into the flowlines. Two adjacent wells are planned to tie into the production manifold. The product is carried through two 12" x 7" nominal diameter pipe-in-pipe flowlines from the manifold to the Marco Polo TLP located 8 miles away. The dual flowline architecture allows round-trip pigging. A multiplex electrohydraulic system will be used to control and monitor the subsea facilities from a Master Control Station (MCS) on the host platform. The MCS will have a data link to shore and a hard-wired link to the platform's emergency fire and gas system. The controls umbilical contains super-duplex stainless steel tubes and electrical quad cables.
Design Challenges
INTEC Engineering has met and overcome the many challenges encountered in this fast-track project. The project is progressing as planned and is within the budget. Installation of the subsea facilities will commence in early November. |
| |
||
| Steady Growth in Brazilian Operations Over the Last 18 Months |
|
Since 1989 INTEC has been providing engineering services to the major oil operator company in Brazil - Petrobras. Notable examples include feasibility studies for oil and gas pipeline designs and installation in deepwater fields and the engineering design of a stinger for the derrick lay barge BGL-1-that improved its pipelaying capability to install pipelines in 200m water depth in the Campos Basin. Another example is the design of the zigzag pipeline in Guanabara Bay to accommodate thermal expansion of a hot pipeline that is cyclically operated and laid on very soft clay.
Transpetro is the company responsible for transportation of oil and gas in Brazil and is 100% controlled by Petrobras. In October, 2003, Transpetro awarded INTEC a year long contract to assess the potential for rehabilitation of pipelines onshore and offshore Brazil. In February, 2004, Petrobras awarded the second long-term contract with an estimated duration of two years that extends the engineering activities to geophysical, geotechnical and oceanographic data acquisition. This created the opportunity for INTEC to recruit and train more young and experienced people with extensive knowledge in data acquisition and pipeline design. Today, the office has grown in staff and the engineering activities are tailor-made to our clients’ needs. INTEC works in close cooperation with Petrobras to help in project organization and to produce project documentation in a format to allow subsequent design verification work by a certifying authority. The Brazilian office is planning its next steps with the vision of providing pipeline and subsea engineering services for projects all over the world. The engineering services in Rio de Janeiro are cost effective and performed with the high degree of quality and competitiveness required in the international arena. The Brazilian office has the potential to provide supportive design work for INTEC global locations - with the highest quality level as established in the INTEC Quality Management System and improving the competitiveness and profitability of worldwide projects. |
| |
||
| A Note from the CEO | ||
|
The Virtual Monopoly
True monopolies are almost always illegal. Some exist, however, at the pleasure of the government, e.g., your local electricity provider. The ability to largely control your own destiny is reason enough to strive to achieve virtual monopoly status, but I think there is more. Being a virtual monopoly also means you are the best at something. You have, know, provide or can create something others cannot. It gives a sense of pride in being part of something unique and better. It is part of creating a work environment where people feel challenged, strive for improvement and do not settle for "good enough." Therefore, I believe trying to build a virtual monopoly is a worthy goal. So how do we build it? The creation of the virtual monopoly is in fact a puzzle in which all the pieces fit together and are held in place by the vision of the company. In our case that vision is: INTEC will be the engineering company of choice for the most challenging marine hydrocarbon developments worldwide. I believe the first piece and the foundation of our virtual monopoly is the hiring, training and retaining of the very best people in each service area we offer. This means making tough decisions like continuing to hire great people when they are available even if it's not the perfect time for us. It also means making equally difficult decisions about where to cut back when the situation warrants it. The next piece is providing a work environment that is conducive to the virtual monopoly formation. By this I mean people must be given a clean and healthy workplace, the proper tools, be provided with motivating challenges and be rewarded for meeting those |
challenges. Most of all, they must be allowed to pursue excellence. Management needs to get out of the way and steer with a light hand. Finally, we must all bring to the company three important ingredients - attitude, attitude and attitude. I mean initiative, drive and flexibility. Everything else the company should provide to you.
The last piece of the puzzle, in my view, is that we must be willing to try lots of small experiments. Like a juggler, we must keep many balls in the air. We then figure out which ones will develop into new service offerings and nurture those, exit the others and try some more. You can see that philosophy in action in our current list of balls - LNG services, Nigerian office, Russian business development, Interface Management, and Risk Management. Maybe not all of these experiments will make it, but regardless we will continue to add and delete as we see new opportunities rise.
I believe we have, to varying degrees, achieved virtual monopolies in several areas. For instance, in May I gave a presentation to the Board of Trustees of the Heerema Group and mentioned the following areas as service offerings where I felt we had a virtual monopoly to some extent:
To close, we have a virtual monopoly in many areas that is surrounded by high barriers. But it is only fleeting if we do not constantly rebuild our walls with good people, a good workplace, exciting challenges and rewards.
Johnny Reed |
|
| |
||
| Modeling of Fluid Flow in the West Delta Deep |
|
Burullus Gas is developing the Simian/Sienna and Sapphire fields, which are located in the West Delta Deep Marine (WDDM) concession, offshore Egypt. These new fields will produce over one billion cubic feet per day of gas via infield pipelines and tie-in manifolds into two main 24-inch and 36-inch trunklines that already transport gas from the existing Scarab/Saffron fields to an onshore terminal. The gas will be exported to the existing NTS distribution network and to a new LNG production facility.
The first WDDM fields to be developed by Burullus, Scarab and Saffron, used INTEC's deepwater expertise and started production in March 2003. Eight deepwater wells are tied into an underwater gas gathering hub in the form of a pipeline end manifold (PLEM), which is connected through the main 65km trunklines to the onshore terminal. With Simian / Sienna Sapphire, the overall tieback length of 114 km makes this one of the longest subsea multiphase tiebacks in the world.
Dynamic Model
Due to the large pipeline capacity, managing offshore liquid hold-up is crucial to the success of the future production operations. INTEC has developed a dynamic model to simulate the impact of changes in both offshore supply and onshore demand on the WDDM pipeline network and the onshore reception facilities. The pipeline and process model has been built using OLGA, a leading multiphase pipeline dynamic simulation package. Using OLGA's recently developed ability to handle diverging as well as converging flow paths, together with a multiphase separator module, INTEC has incorporated the entire subsea network into a model. This model also includes the facilities of the onshore process, including slug catchers, and the high-pressure (HP) and low-pressure (LP) separators. See the schematic (pg. 4). Due to the limited control system functionality within OLGA, a link between OLGA and MATLAB/Simulink has been used, allowing a detailed model of the onshore terminal control functions to be developed in Simulink. This includes a DCS style controller function written specifically for the project by INTEC. This approach has allowed a variety of control system options to be evaluated without changing the OLGA model and without the need for a separate process modeling package for the onshore facilities.
Specific Benefits
The model has also been used to verify the design capacity of the slug catchers, taking into account the maximum liquid handling rates of downstream equipment. This resulted in modifications to the liquid distribution control system design. The modifications maximized the available capacity of the four LP separators under liquid surge conditions in either (or both) of the trunklines and their respective slug catchers.
The modeling of the complete pipeline network and the onshore facilities has also given an insight into the interactions between the fields and between the two trunklines. This has led to the development of preliminary operational strategies for field re-starts, enhancement to the pressure control strategy, and to consideration of field segregation at the PLEM when turn-down in the 36-inch line is no longer an issue. In summary, the OLGA-MATLAB/Simulink model has allowed the project to:
|
| |
||
| Diaries from a Secondee |
|
June 23, 2004
Howdy y'all, I went to a baseball game yesterday - Houston Astros vs. Pittsburgh Pirates... we (I know, but I'm trying to fit in) we won. Once I got the hang of strikes, balls and walks, I was well into it. Except when the ball came towards me. I ducked and prayed it wouldn't hit me. Thing is, I was sitting next to the client. He was trying to catch the ball and I don't think he appreciated me trying to hide behind him!!! They had asked during a meeting if I wanted to go. When I asked what game the Astros played, they all found it highly amusing. But how was I supposed to know what game they played?
The food on offer was unbelievable: jacket potatoes (well I think they were) heaped with heaps of stuff and nachos also heaped with loads of stuff. So I thought I'd play safe and go for a beef fajita. It was huge. Instead of slivers of beef, there were great chunks. Onions and peppers were very few and it had rice in it. Rice and tortilla make a very interesting meal combination, such that 2 bites and you're full!! Other than that, all's well. Have got the hang of driving and am whizzing around all over the place. I now drive with attitude, just like everyone else here. There was a minor incident with a "lady of the night" when I got lost downtown last week, but I survived. Well that's all for now. P.S. If anyone is sending a package out here, please send my heater. The office is very very cold. In fact, everywhere indoors is too cold for me. I only brought 1 jumper with me, and funnily enough I can't find any in the shops!
July 6, 2004
First of all though a few of you want to know about the project (???) and few more actually enjoyed my last email... move over Bill Bryson!! So just to prove that I haven't forgotten why I'm here... The project is going well in a kinda so-far-so-good kind of way. I think you all know that it's called Blind Faith, and contrary to popular belief, this has nothing to do with me being on the team. It is called Blind Faith after a 1960's rock group (I bet Richard knew this), who's most famous member was Eric Clapton. Rock groups are the theme for the area, and yes "Thunder Horse" is or was a rock group. Not sure about Devils Tower and Na Kika, though. And did you know that it's the reservoir engineers who get to name the fields? This phase of the work is the concept phase (pre-FEED to you & me) but ChevronTexaco (CVX) call it Phase 2 (they have this CPDEP process for each phase of a development). It took a while, obviously, to get settled as I had to get to know people and find them around the office as INTEC is spread over 4 floors. Finding stuff on the server and getting up to speed on the work done during the previous phase. But hey, being the star that I am, I'm there now... It's a fairly large team and it's the same set-up as Simian (pre-FEED & FEED) in that we are working with a topsides processing company called EDG. There is also an option to consider a new build FPSO and, although I have nothing to do with it directly, it's very fascinating getting to know the aspects that they have to consider. So purely for my own reasons I hope they go with this option. The team consists of pipelines, risers, subsea hardware, hull/moorings engineers and me. CVX is doing the flow assurance work, but Noel for what it's worth you're still my star in the world of FA (closely followed by Joe, Abu and Dom of course….oh, and you too Atul). So that's it except that this phase is currently scheduled to end around October/November. Ok, so now for the low down of life in Houston... I think I'm giving y'all the wrong impression, there are downsides to living out here you know. So far, I've only given you the highlights so for those of you who think I'm partying, here are the low points.
The Weather And they all say "I bet your used to that?" The answer being NO…..if the total UK rainfall in a year was as much as we've had here in the last 3 weeks, it would be like the Noah Bible story all over again, and I am not exaggerating. I have been composing this email over several weeks and it has actually stopped raining. But there's a downside to that, too, as the long period of out-of-season rain has brought the mosquitoes out in full force. And guess who they're finding tasty? My arms, legs and even my stomach are covered in bites and I'm itching like mad.
The Language Barrier My Own Office When written down it looks good, but it's a bit isolating and as I'm new here I don't socialize like I did back in the UK. This is also isolating from a working point of view; excellent if you were working on a study on your own, but not so good when working as part of a team.
Standard Greeting Even ordinary people in shops and on the street greet me like this. Thing is, I don't know how to reply. I mean, am I supposed to just say I'm fine or should I ask them how they're doing in return? I alternate between the two responses, but the former seems rude and the latter a bit too personal. So now I try and avoid them but they follow you around the shop or just shout it at you so you have to answer.
Their take on England Everyone in England lives in London. They all want to come to England as it's so quaint. One woman said she can't wait to see all the little houses with the thatched roofs! Our accent is so cute and I've just about had it with that word. When I was being shown around an apartment, the lady said that her mother-in-law was English. When I asked if she knew where about, she said Edinburgh. Another friend's wife (English) was told by one of the American moms that she was impressed at how well her kids had picked up the language... that I think tops the lot!!! Insects, animals and flying big things I believe my fear of spiders is legendary. Not any more, give me a UK spider any day over flying cockroach things, wasps the size of small birds, spiders that do serious harm and armadillos. I saw my first armadillo a few days ago; they are so weird looking. It was just mulling around by my apartment. I found a very large cockroach in the kitchen the other morning and even though it was dead it scared the life out of me. Lord only knows what I would have done if it was still alive. The mosquitoes I've already mentioned, and my apartment complex is inundated with frogs, again due to the recent wet weather.
Driving Anyway, I will no longer be reporting on incidents of getting lost as they are a daily occurrence. However, despite the fact that some road signs are on the junction, the road system is logical so I can now get my self un-lost without panicking and/or crying. That's it... Happy (belated) 4th July. |
| |
||
| |
||
| INTEC Engineering, Inc. Intercontinental Building 15600 JFK Boulevard, 9th Floor Houston, TX 77032, USA tel: (281) 987-0800 Primary Fax: (281) 987-3838 Admin Fax: (281) 987-2002 e-mail: info@intec-hou.com |
![]() |
INTEC Engineering (SEA) SDN. BHD. Suite 12.2, 12th Floor Menara Aik Hua Changkat Raja Chulan 50200 Kuala Lumpur, Malaysia Tel: +60 (3) 202-2488 Fax: +60 (3) 202-3488 e-mail: info@intec-mal.com.my |
![]() |
INTEC Engineering B.V. Poortweg 14 2612 PA Delft, The Netherlands P.O. Box 3178 2601 DD Delft, The Netherlands tel: +31 (15) 256-5675 FAX: +31 (015) 256-0194 email: info@intec-delft.com |
![]() | INTEC Engineering S.R.L. Lavalle #465 Planta Baja 1047, Buenos Aires Argentina tel: +54 (1) 14 327-4120 FAX: +54 (1) 14 327-4121 email: info@intec-hou.com |
![]() |
INTEC-egis Adelaide House 200, Adelaide Terrace Perth, Western Australia 6000 tel: + 61 (8) 9220 9374 FAX: + 61 (8) 9325 9897 email: info@intec-hou.com |